110 kV Granit substation

110 kV Granit substationIn Karelia, the construction of the Granit 110 kV substation has begun near the village of Polova. According to the office of the press service of the head of the110 kV Granit substation republic, the new power facility will be built by ROSSETI North-West. It will provide electricity to 8 thousand residents of Prionezhsky and Pryazhinsky districts.

«The new energy infrastructure will solve many pressing social problems,» commented the head of the Republic of Karelia Artur Parfenchikov. — A large number of individual housing is being built on the actively developing territory of Prionezhsky and Pryazhinsky districts.»

The new substation will provide electricity to 8,000 people, as well as hospitals, clinics, kindergartens, schools and the Prionezhskaya Mining Company stone mining and processing enterprise. The commissioning of the substation will create 12.5 megavolt-ampere reserve for connecting new consumers. The launch of the power supply center will provide 7.8 MW of power to the Prionezhskaya Mining Company, the region’s leader in the production of crushed stone.

At the Granit 110 kV substation, we carry out the commissioning of RPA devices, power equipment and secondary switching circuits.:

NDP RPA overhead line, SV and substation,
NDP ALSO includes 110 kV secondary switching circuits,
NDP ALSO includes 35 kV secondary switching circuits,
POLAND KRU 10 kV,
NDT Transformers T1 and T2, TSN — 1,2 and their secondary switching circuits,110 kV Granit substation
NDT test, check the ground loop, as well as the power supply circuits for the building’s own needs,
Development of NDP programs.

110 kV Granit substationThe activation is scheduled for 01.09.25.

It should be recalled that the 110 kV Granit substation will be included in the United Energy System of the North-West, which is part of the Unified Energy System of Russia, being in the operational area of responsibility of the branch of JSC SO UES — Regional Dispatch Management of the Energy System of the Republic of Karelia.

The head of Karelia, Artur Parfenchikov, arrived at the substation construction site and, together with Artem Pidnik, CEO of ROSSETI North-West, laid a time capsule.

«The substation is quite powerful, ROSSETI has not built anything like it in Karelia for more than 10 years. It will provide reliable energy supply to two districts – Prionezhsky and Pryazhinsky,» the head of the republic noted.